The structural steel began arriving on Monday, July 23, and actually began to be erected that same day. The steel is being erected in "sequences". Sequence 1 is the two-story area on the east end of the new building which connects to the O.C. Lewis Gymnasium.

The block walls continue to go up around the building. The next main area of concentration for the blocks will be along the existing main entrance to the Natatorium.